Internationally Renowned Investment Bank
- Data Center and installation of 3 floors completed within 2 months
- Visi-Patch Solution
- Multi floor, 584,000 sf space
- 40 Cabinets meticulously installed and cabled to the specification of client
- Precise Labeling from Data Center to IDFs to locations
- Challenging Fiber Riser Installation
This world-renowned investment bank contracted Cableworx to build a data center and three new floors in Manhattan. Cableworx completed the first phase of building out the data center and Visi-patch horizontal frame, within a two-week of project inception.
Phase Two was completed within four weeks after Phase One: 40 floor fiber riser build out; infrastructure installation of three floors from slab to finished supporting trading desks and back office personnel.
|